division | schedule | detail |
---|---|---|
progress | ||
2003. 10. 30. | Designation of Hadong District as Gwangyang Bay Area Free Economic Zone (Ministry of Finance and Economy) |
|
2008. 09. 12. | Designated as a development project assailant | |
2009. 03. 30. | Development plan change and implementation plan approval (Ministry of Finance and Economy) |
|
2012. 02. 29. | Conclusion of construction contract and commencement of construction (Hanshin Public Works) | |
2012. 05. 02. | Hadong-gun land sales contract concluded (330,000 ㎡) | |
2012. 10. 09. | Construction begins on the sea level (6 light buoys, 17km of anti-fouling membrane completed) | |
2014. 02. 13. | Hanshin Public Works construction halted (1st section vacancy rate: approximately 23%) | |
2017. 10. 13. | Hanshin Public Works lien setting lifted | |
2018. 04. 17. | Implementer Hadong District Development Corporation Co., Ltd. declared bankrupt (Changwon District Court) | |
2022. 12. 01. | Approval of change in implementation plan for Galsaman Industrial Complex in Hadong District (change in development project implementation period until December 31, 2023) |